Local Development Framework Progress Check - Timetable

 

The timetable for preparing the South Lakeland Local Development Framework is set out in full in the 2010 Local Development Scheme. New regulations introduced in June 2008 have modified the prescribed consultation stages.

The milestones for each document and current progress are set out below.

 
LDF Progress Check

Document

Document Stage

Current Position
(April 2010)

2010 LDS Milestones
(start dates)

Statement of Community Involvement (SCI) Submitted to Secretary of State November 2005 Achieved
Examination and Receipt of Inspector's Report July 2006 Achieved
Adoption September 2006 Achieved
Core Strategy (CS) Public Consultation on Issues and Options Commenced November 2005 Achieved
Public Consultation on Preferred Options Commenced April 2008 Achieved - 3 months delay
 

Publication of Core Strategy for representations on soundness

Published for 8 weeks - 27th August to 23rd October 2009 July 2009 - 8 weeks
Submission to Secretary of State Submitted 26 November 2009 October 2009
  Pre Hearing Meeting February 2010 November 2009
Examination Hearing March 2010 January 2010
  Receipt of Inspectors Report (Expected June 2010) July 2010
  Adoption and Publication (Expected August 2010) August 2010
Kendal Canal Head Area Action Plan Public Consultation on Issues and Options Commenced 31 May 2007 Achieved
  Public Consultation on Preferred Options Commenced April 2008 Achieved - 3 month delay
  Further Public Participation on Preferred Options   August 2010
  Publication of Canal Head AAP for representations on soundness   January 2011
  Submission to Secretary of State   April 2011
  Pre Hearing Meeting   July 2011
  Examination Hearings   August 2011
  Receipt of Inspectors Report   November 2011
  Adoption and Publication   December 2011
Allocations of Land DPD and Proposals Map Public participation on Preferred Options

Early consultation commenced

December 2008

September 2010
  Publication of documents for representations on soundness  

February 2011

Submission to Secretary of State  

May 2011

  Pre Hearing Meeting   August 2011
Examination Hearings  

September 2011

  Receipt of Inspectors Report   December 2011
Adoption and Publication  

January 2012

Development Control Generic Policies It is no longer intended to progress this document   ---------  --------
Joint Wind Energy SPD Commencement of Preparation Commenced November 2005 Achieved
  Draft SPD and SA Report Issued for Public Consultation Commenced 31st October 2006 Achieved
  Adoption December 2007 Achieved
Joint Landscape SPD It is no longer intended to progress this document as an SPD. Cumbria County Council is producing Landscape Guidance for the County.         ---------          ---------
Joint Highway Design SPD It is no longer intended to progress this document         ---------          ---------
Annual Monitoring Report (AMR) Report for 2004/5 Submitted December 2005
Achieved
Report for 2005/6 Submitted December 2006
Achieved
Report for 2006/7 Submitted December 2007

Achieved

  Report for 2007/08 December 2008 Achieved
  Report for 2008/09 December 2009 Achieved