Thank you for your patience and understanding during the Kirkland Enhancement Scheme improvement works. The Scheme is progressing on time and to budget and we hope to complete the works on Friday 19th March 2010.

The locations to lay new paving and widen pavements will shortly be changing as detailed below. Loading bays will be made available for affected businesses as part of the temporary one lane operation. Please speak directly with the Thomas Armstrong site manager to advise of regular deliveries or if you are expecting any special access requirements.

Programme of work – (dependent on weather conditions)

Nether Bridge to Wheatsheaf (west side) -  to complete 12 February

Dowker’s Lane to Robinson’s Electrical - to complete 12 February

Wheatsheaf Pub to Gillinggate - 15 February – 26 February

Nether Bridge to Ring of Bells (east side) - 26 February – 12 March

Road markings, installation/ removal of signs - 1 March – 19 March

Installation of new lighting and prismo carriageway paving - 1 March – 19 March