Kirkland Enhancement Scheme
Kirkland News Update No 2 - 20 January 2010
Work has now started on improving Kirkland’s footways and
lighting. The works will last 8 weeks and the areas affected are
listed below. Loading bays will be made available for affected
businesses as part of the temporary one lane operation. Please
speak directly with the Thomas Armstrong site manager to advise of
regular deliveries or if you have any special access
requirements.
Programme of work – geographical areas
- 18 Jan – 2 Feb - Dowkers Lane to Peppercorn
Lane Car Park
- 18 Jan – 14 Feb -Nether Bridge (west) to
Wheatsheaf
- 15 Feb – 12 March - Nether Bridge (east) –
Robinson Electrical
- 3 Feb – 21 Feb - Wheatsheaf Pub to
Gillinggate
- 21 Feb – 21 Mar - Road markings, installation/
removal of signs, Installation of new lighting and prismo
carriageway paving
To see the detailed plans for Kirkland, pedestrian audit reports
and latest news please see www.southlakeland.gov.uk/kirkland